WD6

Project Title: WD6

What was the problem?
Displaced Joints and Obstruction in Pipe. The displaced joints caused leakage of water into the ground, around the pipe.

What the work consisted of?

  • High water pressure Jetting
  • CCTV Survey Condition Report
  • Drainage Layout Plan

Work we performed: 

  • An initial CCTV Drain Survey was suggestively run, and within the findings there were Several Displaced Joints and Obstruction in Pipe.
  • Jetting / Clearance works was recommended in addition to Lining and/or Pipe Replacement.
  • High Pressure Water Jetting was required to remove the blockage at 12.4 meters depth of the sewer. 
  • 2nd step was to install a nine-meter structural liner. 
  • The last step involved a post CCTV survey, which was carried out to beyond the boundary. 
  • The pipes were lined, and the obstructions were removed.
  • Once the work was completed, the site of work was left clean and tidy.