Main Banner

HA3

Project Title: HA3

The problem:
The client had an issue with Overflowing drains

Work involved: 

  • Unblocking
  • Root Removal
  • CCTV Survey Condition Report 
  • Approximate Drainage Layout Plan

What we did?

  • Attended property to conduct works as quoted. 
  • Engineers were able to remove a large amounts roots from within the chamber and immediate drainage runs, allowing for free flow of waste through the manhole and pipes. 
  • The rendering of the manhole was in very poor condition and required to be repaired as soon as possible. 
  • These further works were noted below: 
    • Chopping back of Manhole Rendering
    • Replacement of Manhole Rendering
    • Replacement of Chamber Run Through